Question 1
A retailer reads a managed-network proposal's thirty-minute response commitment as a promise to restore service within thirty minutes. The proposal actually commits an engineer to begin investigating within that time; some faults require the retailer's Internet provider to act. Which contract revision directly addresses the gap between the proposal and the retailer's expectation?
Show answer & explanation
Correct answer: A - Define restoration targets and third-party responsibilities.